Proceedings of the Annual Iowa State University Regulatory Conference on Public Utility Valuation and the Rate Making Process, Volume 26Iowa State University., 1987 |
From inside the book
Results 1-3 of 88
Page 119
... Commission itself may take issue , but this seldom happens . Formal Commission approval , in effect , comes with a rate proceeding's final order . I encourage any regulatory agency not doing this to try it . It has worked extremely well ...
... Commission itself may take issue , but this seldom happens . Formal Commission approval , in effect , comes with a rate proceeding's final order . I encourage any regulatory agency not doing this to try it . It has worked extremely well ...
Page 139
... Commission on the capital structure issue . The court found that the Commission did not explain how it arrived at adjusting NSP's capital structure , and lacking that explanation , the court found the commission's adjustment was not ...
... Commission on the capital structure issue . The court found that the Commission did not explain how it arrived at adjusting NSP's capital structure , and lacking that explanation , the court found the commission's adjustment was not ...
Page 144
... commission observed that industry norms must be taken as merely one indication of whether the company's responses to its problems were reasonable . This commission stated , " If we were to treat industry practices as dispositive , we ...
... commission observed that industry norms must be taken as merely one indication of whether the company's responses to its problems were reasonable . This commission stated , " If we were to treat industry practices as dispositive , we ...
Other editions - View all
Common terms and phrases
accounting ACRS addition adjustment airline allocation allowed alternative minimum tax amount antitrust laws assets AT&T basis benefits BOCs bypass capital recovery carriers cogeneration Commission competition competitors Computer construction consumers corporate income tax cost Court customers December 31 deferred tax depreciation reserve deregulation effect Enron equipment estimated expense facilities federal FERC future impact increased industry inside wire interexchange investment tax credit Iowa State Regulatory issues long distance megawatts method million monopoly natural gas natural monopoly Northern Natural obsolescence operating percent pipeline placed in service plant problems production protect public utility purchase PURPA rate base rate-of-return regulation reduced regular corporate income regulation reserve result retirement revenue SCANA significant social contract supra note survivor curves switching tax liability tax rate Tax Reform Act taxpayer telecommunications telephone companies Texas Transco transitional rules transmission utility's vintage