5. There would be numerous days when little or no progress could be made because of a number of factors, including mechanical breakdowns and adverse weather conditions which would prohibit utilization of the support helicopters. The crew for a unit would consist of about 15 men requiring food A standard drilling rig modified for Arctic work has been found to be the most practical. A 2-1/2 inch split spoon would run through the 9-inch auger for the purpose of driving ahead to test soil strength. The auger would be replaced with a core barrel and drill for taking core samples. Working 10 hours per day, each drilling rig would require an average The cost of drilling each hole would be about $10,000 with the cost of geotechnic field and lab support amounting to $2,500 per hole. Supervision and technical backup would add another $1,500 for a total of about $14,000 per hole, or $77 million for 5500 soil borings. Preliminary Survey Two Years and Nine Months Required. (Ninth month of year 1 through fifth month of year 4) Contracts would have to be prepared for a physical survey and mapping for all civil work including river crossings, road crossings, property surveys, profiles, access roads, material sites, station sites and the main haul road. 6. Prepare Project Description - One Year and Three Months Required. (Sixth month of year 2 through eighth month of year 3) 7. Assuming the description prepared for the Trans-Alaska pipeline would Environmental Impact Statement Preparation (First month of year 3 through third month of year 4) Requisite information for the Environmental Impact Statement would be Following preparation of the Environmental Impact Statements (U. S. and the Canadian equivalent) application for permits would be made. 10. 11. (Seventh month of year 1 through twelfth month of year 3) This time requirement fits within the time frame necessary to accomplish other pre-construction activities and consequently does not add to the overall time estimate. Note, however, that the Canadian Native Claims issue would have to be completed prior to start of construction. U. S. Permit Granted. (Permit issued in middle of year 4) We assume that the main U. S. right-of-way permit would be issued without unreasonable delay. Canadian Permit Granted. (Permit issued at the end of year 4) We assume that the main Canadian right-of-way permit would be issued Government to act since there would be more data to consider and review on the longer segment of line through Canada. (First month of year 3 through twelfth month of year 4) A detailed mile-by-mile design would have to be completed and approved prior to the issuance of U. S. and Canadian notices to proceed with construction (See Item 13). We would plan to complete the mile-by-mile design shortly before the main right-of-way permits are issued, so that we could immediately submit this detailed design to the U. S. Department of Interior (and its Canadian equivalent) for its review and approval. This design would utilize the results of the comprehensive soil boring program. 13. Notices to Proceed Nine Months Required. 14. (Fourth month of year 5 through twelfth month of year 5) After issuance of the main right-of-way permits, the U. S. Department of Interior (and its Canadian equivalent) would conduct a comprehensive review of the mile-by-mile design. This review would be made to ensure that the design would comply with the rigorous criteria and strict construction stipulations established by the U. S. Department of Interior. (We assume that Canada will require the same review procedure and further, that its design criteria and its construction stipulations would be comparable to those required by the U. S. Department of Interior.) After this review, the governmental agencies would issue notices to proceed with construction for those sections where the design has been given final approval. We assume that notice to proceed on the civil work--haul roads, access roads and camps, for example--would be issued before review of pipeline design is completed. Further, we assume that notice to proceed with pipeline construction would be issued by sections, recognizing that notice to proceed with construction of certain pipeline sections in particularly delicate areas might be delayed pending verification of data. Road Construction Two Years and Nine Months Required. (Seventh month of year 4 through third month of year 7) Construction of roads in the United States would begin as soon as the main 15. opposition by environmentalists which has halted construction of a road paralleling the Mackenzie Valley north to Innuvik, and would complete this section of Canadian highway. Construction Surface Two Years and Four Months Required. A gravel pad averaging two to three feet in thickness to permit movement of construction equipment would have to be laid alongside the pipeline route. It would be connected by access roads to the main haul roads. This gravel pad would allow year-round access by maintenance equipment after operations begin. 16. Rights-of-Way Purchase Three Years Required. 17. 18. (Tenth month of year 2 through ninth month of year 5) The Canadian pipeline would cross mostly private lands south of Edmonton Commitments for Camps and Buildings - Seven Months Required. (First month of year 5 through seventh month of year 5) Commitments for camps and supporting services would not be made until the main right-of-way permits were received from the United States and Canada. Commitment for Construction Equipment and Manufacture (First month of year 5 through ninth month of year 5) Nine Commitments for construction equipment such as ditchers, pipe benders, 19. Negotiate Construction Contracts - Six Months Required. (First month of year 5 through sixth month of year 5) Serious negotiations with contractors for pipeline construction would not 21. South of Edmonton. Two Years and Ten Months Required. Pipeline construction would start south of Edmonton after obtaining Main Line Construction North of Edmonton Three Years and Three Months Required. Pipeline construction could begin north of Edmonton as additional equip- We assume a pipeline construction rate of 2500 feet per day for each (Tenth month of year 9 through tenth month of year 10) The medium to be used for testing the line; i.e., gas or liquid, has yet to be selected. If a liquid medium were to be used, testing in the mountainous areas would have to be done by sections. Moreover, if a |