Construction Scheduling and ControlMcGraw-Hill, 1965 - 316 pages |
From inside the book
Results 1-3 of 42
Page 23
... authority in the field , ad- justed to concur with his experience , and time values are placed on the job conditions under which the work is to be done . 3. That subdivisional part of the work being estimated for time is made the ...
... authority in the field , ad- justed to concur with his experience , and time values are placed on the job conditions under which the work is to be done . 3. That subdivisional part of the work being estimated for time is made the ...
Page 65
... Authority to Originate Purchases There are usually only three sources of authority by which purchases may be origi- nated : 1. By B / Ms originating in the engineering department , comprising materials or equip- ment called for on the ...
... Authority to Originate Purchases There are usually only three sources of authority by which purchases may be origi- nated : 1. By B / Ms originating in the engineering department , comprising materials or equip- ment called for on the ...
Page 197
... authority , the chief tool keeper will note his O.K. and initials on the tool receipt , which is authority for the toolroom attendant to issue the tools to the subcontractor representative . Care must be exercised by the attendant to ...
... authority , the chief tool keeper will note his O.K. and initials on the tool receipt , which is authority for the toolroom attendant to issue the tools to the subcontractor representative . Care must be exercised by the attendant to ...
Contents
Construction Scheduling | 1 |
Purchasing | 119 |
Materials Expediting and Transportation | 145 |
Copyright | |
8 other sections not shown
Common terms and phrases
agreement apply approval arbitration Architect ARTICLE Associated General Contractors bar chart bill of lading bill of material bolt building cable carrier charges chart completion concrete conehead consignee construction contract contractor copy cost covered damage Deatherage delivery demurrage drawings and specifications employee employment engineering equipment erection estimate foreman freight furnish handling inspection issued labor liability load manager ment method necessary operation organization owner party payment performed person pipe pipe Wrenches plans procedure Punches purchase order purchasing agent rates Reamers received record rental requisition rope safety safety engineer scaffolds schedule secured sheet shipment shipper standard steel erector structural steel subcontractor superintendent supply taper shank Drill temporary terials thereof tion Toledo tractor trucks unloading VALVE vendor wages wire Wrenches