Construction Scheduling and ControlMcGraw-Hill, 1965 - 316 pages |
From inside the book
Results 1-3 of 92
Page 108
... contractor or owner . 6. LIENS : Subcontractor further agrees to pay and indemnify the contractor from and against all losses , liabilities , suits , or obligations of every kind paid or incurred by the contractor on account of the ...
... contractor or owner . 6. LIENS : Subcontractor further agrees to pay and indemnify the contractor from and against all losses , liabilities , suits , or obligations of every kind paid or incurred by the contractor on account of the ...
Page 123
... contractor by agreement or arbitration , if he will so settle . If such separate con- tractor sues the Owner on account of any damage al- leged to have been so sustained , the Owner shall notify the Contractor , who shall defend such ...
... contractor by agreement or arbitration , if he will so settle . If such separate con- tractor sues the Owner on account of any damage al- leged to have been so sustained , the Owner shall notify the Contractor , who shall defend such ...
Page 134
... contractor does not guarantee the con- tinuous functioning of any service now on the site or subsequently to be installed . In no case shall the contractor be held responsible for loss or delay by the subcontractor by reason of ...
... contractor does not guarantee the con- tinuous functioning of any service now on the site or subsequently to be installed . In no case shall the contractor be held responsible for loss or delay by the subcontractor by reason of ...
Contents
Construction Scheduling | 1 |
Purchasing | 119 |
Materials Expediting and Transportation | 145 |
Copyright | |
8 other sections not shown
Common terms and phrases
agreement apply approval arbitration Architect ARTICLE Associated General Contractors bar chart bill of lading bill of material bolt building cable carrier charges chart completion concrete conehead consignee construction contract contractor copy cost covered damage Deatherage delivery demurrage drawings and specifications employee employment engineering equipment erection estimate foreman freight furnish handling inspection issued labor liability load manager ment method necessary operation organization owner party payment performed person pipe pipe Wrenches plans procedure Punches purchase order purchasing agent rates Reamers received record rental requisition rope safety safety engineer scaffolds schedule secured sheet shipment shipper standard steel erector structural steel subcontractor superintendent supply taper shank Drill temporary terials thereof tion Toledo tractor trucks unloading VALVE vendor wages wire Wrenches