identified by independent circumstances, such as all those deposited in a certain warehouse, or to be shipped in a particular vessel, or that may be manufactured by the seller, or may be required for use by the buyer, in a certain mill-in which case the mention of the quantity, accompanied by the qualification of "about," or "more or less," is regarded as a mere estimate of the probable amount, as to which good faith is all that is required of the party making it. But the contract before us comes within the general rule: "When no such independent circumstances are referred to, and the engagement is to furnish goods of a certain quality or character to a certain amount, the quantity specified is material, and governs the contract. The addition of the qualifying words 'about,' 'more or less,' and the like, in such cases, is only for the purpose of providing against accidental variations, arising from slight and unimportant excesses or deficiencies in number, measure, or weight." Brawley v. United States, 96 U. S. 168, 171, 172.

The seller is bound to deliver the quantity stipulated, and has no right either to compel the buyer to accept a less quantity, or to require him to select part out of a greater quantity; and when the goods are to be shipped in certain proportions monthly, the seller's failure to ship the required quantity in the first month gives the buyer the same right to rescind the whole contract, that he would have had if it had been agreed that all the goods should be delivered at once.

The plaintiff, instead of shipping about 1000 tons in February and about 1000 tons in March, as stipulated in the contract, shipped only 400 tons in February and 885 tons in March. His failure to fulfill the contract on his part in respect to these first two instalments justified the defendants in rescinding the whole contract, provided they distinctly and seasonably asserted the right of rescission.

The defendants, immediately after the arrival of the March shipments, and as soon as they knew that the quantities which had been shipped in February and in March were less than the contract called for, clearly and positively asserted the right to rescind if the law entitled them to do so. Their previous acceptance of the single cargo of 400 tons shipped in February was no waiver of this right, because it took place without notice, or means of knowledge, that the stipulated quantity had not been shipped in February. The price paid by them for that cargo being above the market value, the plaintiff suffered no injury by the omission of the defendants

to return the iron; and no reliance was placed on that omission in the correspondence between the parties.

The case wholly differs from that of Lyon v. Bertram (20 How. 149), in which the buyer of a specific lot of goods accepted and used part of them with full means of previously ascertaining whether they conformed to the contract.

The plaintiff, denying the defendants' right to rescind, and asserting that the contract was still in force, was bound to show such performance on his part as entitled him to demand performance on their part, and, having failed to do so, cannot maintain this action.

For these reasons, we are of opinion that the judgment below should be affirmed. But as much of the argument at the bar was devoted to a discussion of the recent English cases, and as a diversity in the law, as administered on the two sides of the Atlantic, concerning the interpretation and effect of commercial contracts. of this kind, is greatly to be deprecated, it is proper to add that upon a careful examination of the cases referred to they do not appear to us to establish any rule inconsistent with our conclusion.

In the leading case of Hoare v. Rennie (5 H. & N. 19), which was an action upon a contract of sale of 667 tons of bar iron, to be shipped from Sweden in June, July, August and September, and in about equal portions each month, at a certain price payable on delivery, the declaration alleged that the plaintiffs performed all things necessary to entitle them to have the contract performed by the defendants, and were ready and willing to perform the contract on their part, and in June shipped a certain portion of the iron, and within a reasonable time afterwards offered to deliver to the defendants the portion so shipped, but the defendants refused to receive it, and gave notice to the plaintiffs that they would not accept the rest. The defendants pleaded that the shipment in June was of about 20 tons only, and that the plaintiffs failed to complete the shipment for that month according to the contract. Upon demurrer to the pleas, it was argued for the plaintiffs that the shipment of about one-fourth of the iron in each month was not a condition precedent, and that the defendants' only remedy for a failure to ship that quantity was by a cross action. But judgment was given for the defendants, Chief Baron Pollock say-. ing:

"The defendants refused to accept the first shipment, because, as they say, it was not a performance, but a breach of the contract. Where parties

have made an agreement for themselves, the courts ought not to make another for them. Here they say that in the events that have happened one-fourth shall be shipped in each month, and we cannot say that they meant to accept any other quantity. At the outset, the plaintiffs failed to tender the quantity according to the contract; they tendered a much less quantity. The defendants had a right to say that this was no performance of the contract, and they were no more bound to accept the short quantity than if a single delivery had been contracted for. Therefore the pleas are an answer to the action.' 5 H. & N. 28.

[ocr errors]

So in Coddington v. Paleologo (L. R. 2 Ex. 193), while there was a division of opinion upon the question whether a contract to supply goods "delivering on April 17, complete 8th May," bound the seller to begin delivering on April 17, all the judges agreed that if it did, and the seller made no delivery on that day, the buyer might rescind the contract.

On the other hand, in Simpson v. Crippin (L. R. 8 Q. B. 14), under a contract to supply from 6000 to 8000 tons of coal, to be taken by the buyer's wagons from the seller's colliery in equal monthly quantities for twelve months, the buyer sent wagons for only 150 tons during the first month; and it was held that this did not entitle the seller to annul the contract and decline to deliver any more coal, but that his only remedy was by an action for damages. And in Brandt v. Lawrence (1 Q. B. D. 344), in which the contract was for the purchase of 4500 quarters, ten per cent more or less, of Russian oats, "shipment by steamer or steamers during February," or, in case of ice preventing shipment, then immediately upon the opening of navigation, and 1139 quarters were shipped by one steamer in time, and 3361 quarters were shipped too late, it was held that the buyer was bound to accept the 1139 quarters, and was liable to an action by the seller for refusing to accept them.

Such being the condition of the law of England as declared in the lower courts, the case of Bowes v. Shand, after conflicting decisions in the Queen's Bench Division and the Court of Appeal, was finally determined by the House of Lords. 1 Q. B. D. 470; 2 Q. B. D. 112; 2 App. Cas. 455.

In that case, two contracts were made in London, each for the sale of 300 tons of "Madras rice, to be shipped at Madras or coast, for this port, during the months of March (and or) April, 1874, per Rajah of Cochin." The 600 tons filled 8200 bags, of which 7120 bags were put on board and bills of lading signed in February; and for the rest, consisting of 1030 bags put on board in

February, and 50 in March, the bill of lading was signed in March. At the trial of an action by the seller against the buyer for refusing to accept the cargo, evidence was given that rice shipped in February would be the spring crop, and quite as good as rice shipped in March or April. Yet the House of Lords held that the action could not be maintained, because the meaning of the contract, as apparent upon its face, was that all the rice must be put on board in March and April, or in one of those months.

In the opinions there delivered the general principles underlying this class of cases are most clearly and satisfactorily stated. It will be sufficient to quote a few passages from two of those opinions. Lord Chancellor Cairns said:

"It does not appear to me to be a question for your Lordships, or for any court, to consider whether that is a contract which bears upon the face of it some reason, some explanation, why it was made in that form, and why the stipulation is made that the shipment should be during these particular months. It is a mercantile contract, and merchants are not in the habit of placing upon their contracts stipulations to which they do not attach some value and importance." 2 App. Cas. 463. "If it be admitted that the literal meaning would imply that the whole quantity must be put on board during a specified time, it is no answer to that literal meaning, it is no observation which can dispose of, or get rid of, or displace, that literal meaning, to say that it puts an additional burden on the seller, without a corresponding benefit to the purchaser; that is a matter of which the seller and the purchaser are the best judges. Nor is it any reason for saying that it would be a means by which purchasers, without any real cause, would frequently obtain an excuse for rejecting contracts when prices had dropped. The nonfulfillment of any term in any contract is a means by which a purchaser is able to get rid of the contract when prices have dropped; but that is no reason why a term which is found in a contract should not be fulfilled." pp. 465, 466. "It was suggested that even if the construction of the contract be as I have stated, still if the rice was not put on board in the particular months, that would not be a reason which would justify the appellants in having rejected the rice altogether, but that it might afford a ground for a cross action by them if they could show that any particular damage resulted to them from the rice not having been put on board in the months in question. My Lords, I cannot think that there is any foundation whatever for that argument. If the construction of the contract be as I have said, that it bears that the rice is to be put on board in the months in question, that is part of the description of the subject matter of what is sold. What is sold is not 300 tons of rice in gross or in general. It is 300 tons of Madras rice to be put on board at Madras during the particular months."' "The plaintiff, who sues upon that contract, has not

launched his case until he has shown that he has tendered that thing which has been contracted for, and if he is unable to show that, he cannot claim any damages for the nonfulfillment of the contract.'' pp. 467, 468.

Lord Blackburn said:

"If the description of the article tendered is different in any respect, it is not the article bargained for, and the other party is not bound to take it. I think in this case what the parties bargained for was rice, shipped at Madras or the coast of Madras. Equally good rice might have been shipped a little to the north or a little to the south of the coast of Madras. I do not quite know what the boundary is, and probably equally good rice might have been shipped in February as was shipped in March, or equally good rice might have been shipped in May as was shipped in April, and I dare say equally good rice might have been put on board another ship as that which was put on board the Rajah of Cochin. But the parties have chosen, for reasons best known to themselves, to say: We bargain to take rice, shipped in this particular region, at that particular time, on board that particular ship; and before the defendants can be compelled to take anything in fulfillment of that contract it must be shown not merely that it is equally good, but that it is the same article as they have bargained for-otherwise they are not bound to take it." 2 App. Cas. 480, 481.

Soon after that decision of the House of Lords, two cases were determined in the Court of Appeal. In Reuter v. Sala (4 C. P. D. 239), under a contract for the sale of "about twenty-five tons (more or less) black pepper, October (and or) November shipment, from Penang to London, the name of the vessel or vessels, marks and full particulars to be declared to the buyer in writing within sixty days from date of bill of lading," the seller, within the sixty days, declared twenty-five tons by a particular vessel, of which only twenty tons were shipped in November, and five tons in December; and it was held that the buyer had the right to refuse to receive any part of the pepper. In Honck v. Muller (7 Q. B. D. 92), under a contract for the sale of 2000 tons of pig iron, to be delivered to the buyer free on board at the maker's wharf "in November, or equally over November, December, and January next," the buyer failed to take any iron in November, but demanded delivery of one-third in December and one-third in January; and it was held that the seller was justified in refusing to deliver, and in giving notice to the buyer that he considered the contract as canceled by the buyer's not taking any iron in November.

The plaintiff in the case at bar greatly relied on the very recent decision of the House of Lords in Mersey Co. v. Naylor (9 App.