The Owner agrees to provide all labor and materials not included in this contract in such manner as not to delay the material progress of the work... Current Law - Page 3751904Full view - About this book
| Michigan. Supreme Court, Randolph Manning, George C. Gibbs, Thomas McIntyre Cooley, Elijah W. Meddaugh, William Jennison, Hovey K. Clarke, Hoyt Post, Henry Allen Chaney, William Dudley Fuller, John Adams Brooks, Marquis B. Eaton, Herschel Bouton Lazell, James M. Reasoner, Richard W. Cooper - 1916 - 802 pages
...not obliterated. It reads: "The owner agrees to provide all labor and materials not included in this contract in such manner as not to delay the material progress of the work, and in the event of failure so to do, thereby causing loss to the contractor, agrees that he will reimburse... | |
| 1904 - 1132 pages
...work mentioned in the specifications; and the defendants agreed to provide all labor and materials not included In the contract, "in such manner as not to delay the material progress of the work; aud in the event of failure to do so, thereby causing loss to the contractor" (the plaintiff), to "reimburse... | |
| Theodore Minot Clark - 1894 - 424 pages
...this contract. ART. VIII. The Owner agrees to provide all labor and materials not included in this contract in such manner as not to delay the material progress of the work, and in the event of failure so to do, thereby causing loss to the Contractor, Form i. agrees that he will... | |
| Theodore Minot Clark - 1894 - 432 pages
...this contract. ART. VIII. The Owner agrees to provide all labor aud materials not included in this contract in such manner as not to delay the material progress of the work, and in the event of failure so to do, therebv causing loss to the Contractor, Form i. agrees that he will... | |
| National Association of Builders of the United States of America - 1894 - 274 pages
...please read Article VIII: — The owner agrees to provide all labor and materials not included in this contract in such manner as not to delay the material progress of the work, and in the event of the failure so to do, thereby causing loss to the contractor, agrees that he will reimburse... | |
| District of Columbia. Court of Appeals - 1902 - 670 pages
...plaintiff's contention must fail. " The owner agrees to provide all labor #nd materials not included in this contract in such manner as not to delay the material progress of the work." What labor and materials ? Can it be said that by this vague and meaningless language the defendant... | |
| Earle Abbott Merrilol - 1896 - 232 pages
...of this contract. ART. vm. The Owner agrees to provide all labor and materials not included in this contract in such manner as not to delay the material progress of the work, and in the event of failure so to do, thereby causing loss to the Contractor, agrees that he will reimburse... | |
| Earle Abbott Merrill - 1896 - 222 pages
...of this contract. ART. vin. The Owner agrees to provide all labor and materials not included in this contract in such manner as not to delay the material progress of the work, and in the event of failure so to do, thereby causing loss to the Contractor, agrees that he will reimburse... | |
| American Society of Mechanical Engineers - 1901 - 1776 pages
...this contract. ART. VIII. The Owner agrees to provide all labor and materials not included in this contract in such manner as not to delay the material progress of the work, and in the event of failure so to do, thereby causing loss to the Contractor, agrees that he will reimburse... | |
| 1903 - 660 pages
...of this contract ART. VIII. The Owner agrees to provide all labor and materials not included in this contract in such manner as not to delay the material progress of the work, and in the event of failure so to do, thereby causing loss to the Contractor, agrees that he will reimburse... | |
| |