" The Owner agrees to provide all labor and materials not included in this contract in such manner as not to delay the material progress of the work... "
Current Law - Page 375
1904
Full view - About this book

Michigan Reports: Cases Decided in the Supreme Court of Michigan, Volume 186

Michigan. Supreme Court, Randolph Manning, George C. Gibbs, Thomas McIntyre Cooley, Elijah W. Meddaugh, William Jennison, Hovey K. Clarke, Hoyt Post, Henry Allen Chaney, William Dudley Fuller, John Adams Brooks, Marquis B. Eaton, Herschel Bouton Lazell, James M. Reasoner, Richard W. Cooper - 1916 - 802 pages
...not obliterated. It reads: "The owner agrees to provide all labor and materials not included in this contract in such manner as not to delay the material progress of the work, and in the event of failure so to do, thereby causing loss to the contractor, agrees that he will reimburse...
Full view - About this book

The Atlantic Reporter, Volume 58

1904 - 1132 pages
...work mentioned in the specifications; and the defendants agreed to provide all labor and materials not included In the contract, "in such manner as not to delay the material progress of the work; aud in the event of failure to do so, thereby causing loss to the contractor" (the plaintiff), to "reimburse...
Full view - About this book

Architect, Owner and Builder Before the Law: A Summary of American and ...

Theodore Minot Clark - 1894 - 424 pages
...this contract. ART. VIII. The Owner agrees to provide all labor and materials not included in this contract in such manner as not to delay the material progress of the work, and in the event of failure so to do, thereby causing loss to the Contractor, Form i. agrees that he will...
Full view - About this book

Architect, Owner and Builder Before the Law: A Summary of American and ...

Theodore Minot Clark - 1894 - 432 pages
...this contract. ART. VIII. The Owner agrees to provide all labor aud materials not included in this contract in such manner as not to delay the material progress of the work, and in the event of failure so to do, therebv causing loss to the Contractor, Form i. agrees that he will...
Full view - About this book

Official Report ... Annual Convention, Volume 8, Part 1894

National Association of Builders of the United States of America - 1894 - 274 pages
...please read Article VIII: — The owner agrees to provide all labor and materials not included in this contract in such manner as not to delay the material progress of the work, and in the event of the failure so to do, thereby causing loss to the contractor, agrees that he will reimburse...
Full view - About this book

Reports of Cases Adjudged in the Court of Appeals of the District ..., Volume 18

District of Columbia. Court of Appeals - 1902 - 670 pages
...plaintiff's contention must fail. " The owner agrees to provide all labor #nd materials not included in this contract in such manner as not to delay the material progress of the work." What labor and materials ? Can it be said that by this vague and meaningless language the defendant...
Full view - About this book

Electric Lighting Specifications

Earle Abbott Merrilol - 1896 - 232 pages
...of this contract. ART. vm. The Owner agrees to provide all labor and materials not included in this contract in such manner as not to delay the material progress of the work, and in the event of failure so to do, thereby causing loss to the Contractor, agrees that he will reimburse...
Full view - About this book

Electric Lighting Specifications for the Use of Engineers and Architects

Earle Abbott Merrill - 1896 - 222 pages
...of this contract. ART. vin. The Owner agrees to provide all labor and materials not included in this contract in such manner as not to delay the material progress of the work, and in the event of failure so to do, thereby causing loss to the Contractor, agrees that he will reimburse...
Full view - About this book

Transactions of the American Society of Mechanical Engineers, Volume 22

American Society of Mechanical Engineers - 1901 - 1776 pages
...this contract. ART. VIII. The Owner agrees to provide all labor and materials not included in this contract in such manner as not to delay the material progress of the work, and in the event of failure so to do, thereby causing loss to the Contractor, agrees that he will reimburse...
Full view - About this book

International Library of Technology: A Series of Textbooks for ..., Volume 31

1903 - 660 pages
...of this contract ART. VIII. The Owner agrees to provide all labor and materials not included in this contract in such manner as not to delay the material progress of the work, and in the event of failure so to do, thereby causing loss to the Contractor, agrees that he will reimburse...